Milestones

15

Open Tasks

2

Completed

0

Customer Pending

2

Vendor Pending

0

Add Task

New Project Task

Milestones

Milestone Progress

#1

Project Kickoff

Project Owner · 16 Jun 2026 → 16 Jun 2026

In Progress

#2

Team Assignment

Project Owner · 17 Jun 2026 → 17 Jun 2026

Not Started

#3

Site Survey

On-site Coordinator · 18 Jun 2026 → 19 Jun 2026

Not Started

#4

Infrastructure Readiness

Backend Coordinator · 20 Jun 2026 → 22 Jun 2026

Not Started

#5

Server / Client Installation

Support Engineer · 23 Jun 2026 → 24 Jun 2026

Not Started

#6

Camera and Capture Setup

VastramAI AI Setup Engineer · 25 Jun 2026 → 26 Jun 2026

Not Started

#7

SoftVAT ERP+ Configuration

SoftVAT ERP Installation Engineer · 27 Jun 2026 → 28 Jun 2026

Not Started

#8

Product / Saree Master Setup

Data / Inventory Coordinator · 29 Jun 2026 → 02 Jul 2026

Not Started

#9

Saree Image Capture and AI Processing

Data / Inventory Coordinator · 03 Jul 2026 → 07 Jul 2026

Not Started

#10

Barcode / QR Printing and Tagging

On-site Coordinator · 08 Jul 2026 → 10 Jul 2026

Not Started

#11

Sales Team Training

Training Coordinator · 11 Jul 2026 → 12 Jul 2026

Not Started

#12

UAT

QA / UAT Coordinator · 13 Jul 2026 → 14 Jul 2026

Not Started

#13

Go-Live

Project Owner · 15 Jul 2026 → 15 Jul 2026

Not Started

#14

Post Go-Live Support

Support Engineer · 16 Jul 2026 → 22 Jul 2026

Not Started

#15

AMC / Ongoing Support

Support Engineer · 23 Jul 2026 → 21 Aug 2026

Not Started

Tasks

Task Control Board

PT-202606-00002

PO Release to Photography Vendor

Saree Image Capture and AI Processing · Due: 17 Jun 2026

MediumTo Do

Need To Capture All Existing Stock Saree Designs Photos

Role: Customer Project Coordinator

Department: Customer Side

Planned: 17 Jun 2026

Completed: -

Customer Visible: YesCustomer Action: YesVendor Action: NoEvidence: Yes

PT-202606-00001

PO Release to Hardware Vendor

Project Kickoff · Due: 17 Jun 2026

HighTo Do

Immediately Release PO to Computer Sullier Vendor

Role: Customer Project Coordinator

Department: Customer Side

Planned: 17 Jun 2026

Completed: -